Monday, July 14, 2014

June, 2014 update

Seeing the light at the end of the tunnel, we're almost there!

Installation of curb and gutter is substantially complete and installation of the graded aggregate paving base has been installed. Concrete sidewalk construction is 98% complete and concrete paving at the dumpster pads has been completed. Concrete pads have been poured for the community garden, picnic area, and other areas where site amenities are located. Connection of utility services to the buildings has been completed, including sanitary sewer and water meters. Permanent power was noted to be in place at buildings 2, 3 and 5.

Construction of building structures has progressed to substantial completion!!   Installation of foundation walls, footings, under-slab plumbing, concrete slabs, and rough framing has been completed. Dry-in activities are complete as all roofing, house wrap, window and entry door/patio door installation are now complete.
MEP rough-in work is now complete and finishes are in progress at each building.

Installation of brick veneer, soffit, fascia and siding was found to be substantially complete.  Construction of the roof additions over the breezeways stairs has been completed and include roofing shingles and siding repairs.  Exterior painting has occurred at each building and is estimated to be 85% complete. Installation of porch and breezeway railings has been completed at Building 600 and is underway at Building 200 and 500. HVAC condensing units have been set at buildings 200, 500 and 600 and breezeway lighting fixtures were confirmed to be installed at Building 600.

Interior finishes have progressed well and drywall installation is now complete at all buildings with finishing of the drywall remaining to be completed only at Building 400. Installation of interior trim, doors and the prime coat of paint are complete at buildings 200, 300, 500 and 600 and interior painting is estimated to be 85% complete at buildings 200, 500 and 600. Cabinetry, electrical devices, plumbing fixtures, and appliances are now installed at buildings 200, 500 and 600m and installation of door and bath hardware, shelving, and mirrors is underway at each of these buildings. Laminated vinyl plank and sheet vinyl flooring have also been installed at buildings 200, 500 and 600.


Check out some of the latest pictures from the construction site and, as always, please leave comments on this blog or contact us via email (info@peachtreehousing.com) with any comments or concerns you may have.