Wednesday, December 4, 2013

November, 2013 update

November, 2013
Now the fun starts!  Framing underway at the community building!
Construction of building structures has progressed well. Construction of all foundation walls and waterproofing is now complete and modular-block wing wall extensions have been completed at buildings 200, 500, and 600. Both under and over-slab plumbing is under way on all buildings and complete on three.
Concrete slabs have been poured at the Community Building, at the lower side of Building 200, and at the upper and lower sides of buildings 500 and 600.
Framing activities have just commenced. Framing is currently under way at the Community Building which is estimated to be around 75% framed. Framing of the lower-level walls was also found to be under way at Building 600. A limited amount of framing materials is currently on-site including floor trusses for Building 600. Framing progress is expected to increase now that the Thanksgiving holiday is over.

Check out some of the latest pictures from the construction site and, as always, please leave comments on this blog or contact us via email (info@peachtreehousing.com) with any comments or concerns you may have.






Wednesday, October 30, 2013

October, 2013 update

Grading almost complete and footings are being poured.
Mass grading is almost complete.  Installation of site utilities has progressed and installation of the water main, sanitary sewer and storm drainage is now complete along the west side of the gas pipeline right-of-way.  Under-slab plumbing and perimeter strip footings are now complete at Buildings 100, 500 and 600.  Next month we should start framing.

Check out some of the latest pictures from the construction site and, as always, please leave comments on this blog or contact us via email (info@peachtreehousing.com) with any comments or concerns you may have.







Friday, September 27, 2013

Site prepping for slab pouring-September, 2013

The lower slabs on all buildings are at sub-grade.  The sewer main and service is in at four out of five buildings.  Foundation wall footings are in at three out of five buildings.  We’re moving right along and staying on schedule!

Check out some of the latest pictures from the construction site and, as always, please leave comments on this blog or contact us via email (info@peachtreehousing.com) with any comments or concerns you may have.






Thursday, August 29, 2013

Here we go!!-August 2013

We’ve started construction and things are officially moving along.  The initial clearing of the site is complete.  Erosion control devices are in place.  The construction entrance is complete and any driving by the site can see that we’re hard at work! 


Check out some of the latest pictures from the construction site and, as always, please leave comments on this blog or contact us via email (info@peachtreehousing.com) with any comments or concerns you may have.






Tuesday, April 16, 2013

Conners Senior Village Phase II coming soon!!

Peachtree Housing and Neighborhood Concepts are proud to announce that Conners Senior Village Phase II will commence construction soon!

Conners Senior Village Phase II (“Phase II”) will be an additional planned sixty unit apartment community designed for seniors (age 55 and older).  Just like Conners Senior Village Phase I (“Phase I”), Phase II will be located in Villa Rica, GA off of Conners Road, adjacent to Mirror Lake and Phase I. Phase II is the second and final phase of the Conners Senior Village master planned phased project.  Phase II will provide its residents with numerous amenities, including a fitness center, a computer center, a large all-purpose community building for community events, a garden for our residents' use, a picnic pavilion and a walking path that meanders through the open space of the property.

Furthermore, Phase II is working on becoming a designated EarthCraft Community.  Conners Senior Village Phase I is already a designated EarthCraft Community.

EarthCraft Communities offers holistic approaches to development for rural, suburban or urban projects. Through the EarthCraft certification process, communities enhance their health, livability, efficiency and overall market appeal. The EarthCraft Communities program addresses low-impact development, site selection, land disturbance, water quality and quantity management, energy, transportation infrastructure, community design, green space preservation and more. In addition, all buildings within an EarthCraft Community must be certified through the EarthCraft House, Multifamily or Light Commercial programs. EarthCraft Communities program administrators perform regular site visits, facilitate conceptual design charrettes and provide each project green building trainings for residents, property managers, builders and/or realtors.

Sustainability will be a large component in the development of and the operation of Phase II.  This focus on sustainability will ensure that our residents live in an environment that is healthy for them, the surrounding community and the environment as a whole.  Obtaining the EarthCraft Communities designation allows for third party inspections and verification to ensure the goal of sustainability is realized.

Phase II of Conners Senior Village will be an additional asset not only to the seniors who reside with us, but also to Villa Rica as a whole.  We look forward to working with the Villa Rica community to bring the final phase of this development to fruition and to continuing our involvement with the Villa Rica community.
We want to ensure the community stays up to date with the plans and progress of our development.  As such, if you have any questions or would like to send us a comment regarding Phase II or Phase I of Conners Senior Village, please either post a comment on the blog or send us an email at info@peachtreehousing.com.  Please use this email for questions or comments regarding the development process only.  For information regarding pre-leasing, please email conners@fairwaymanagement.com or call 770-459-2933.

Please visit this blog often as we will be posting updated pictures and blogs throughout the construction of Conners.


Below is the site plan for Conners.