Saturday, December 31, 2011

December 2011 Update (Rain, Rain, Go Away...)

Once again, despite the nearly constant rainy conditions, construction is progressing well.  The pictures below are indicative of the weather we've experienced for the last month.  Alas, we are undeterred.  We are pressing on.

Site work is now 65% complete.  The initial site work including clearing, grubbing, mass grading and instalation of underground infrastructure is 100% complete.  Installation of curb and gutter is 95% complete.

The building construction has been limited to the slabs being poured, but framing materials are on site and awaiting dry weather...