Thursday, March 20, 2014

February, 2014 update

February, 2014
Rough winter we’re having but progress continues.

Construction of building structures continues to progress despite less-than-optimal weather conditions over the past month.  Construction of all foundation walls, waterproofing, under-slab plumbing, and concrete slabs-on-grade are now complete. Framing activities continue to progress and are estimated to be 85%complete. Framing is complete at the Community Building and buildings 200, 500, and 600. Terrace-level walls and floor systems for the main-level floor are now in place at buildings 300 and 400. Wall crews were in the process of framing the main level walls. Wood stairs, breezeway landing, and balcony framing is now complete at buildings 200, 500, and 600. Dry-in activities have also progressed as roofing, house wrap, and windows are installed at the Community Building and buildings 200, 500, and 600. Shingles for the remainder of the project are stored on-site. Windows are also on-site for the remaining two buildings.

HVAC rough-in was estimated to be 75% complete at Building 200, 95% complete at Building 500, and 10% complete at Building 600. Installation of drywall for attic draftstopping was found to be complete at buildings 200 and 500 along with “pre-rock” installation within the HVAC closets.


Check out some of the latest pictures from the construction site and, as always, please leave comments on this blog or contact us via email (info@peachtreehousing.com) with any comments or concerns you may have.







Wednesday, February 19, 2014

January, 2014 update

January, 2014

Moving along…

Framing activities continue to progress and are 65-70% complete. Framing is complete at the Community Building, Building 200 and Building 500. Installation of roof decking was underway at Building 600. Stair and deck framing is complete at Buildings 200 and 500.

Dry-in activities have also progressed as roofing is now in place at the Community Building, Building 200, and Building 500. MEP rough-in is now underway. Plumbing rough-in was is 90% complete at Buildings 200 and 500, with only installation of tubs remaining to be completed. Fire sprinkler and electrical rough-in are complete at Buildings 200 and 500. HVAC rough-in is complete at Building 500 and approximately 90% complete at Building 200 and the Community Building.

Check out some of the latest pictures from the construction site and, as always, please leave comments on this blog or contact us via email (info@peachtreehousing.com) with any comments or concerns you may have.








Friday, January 3, 2014

December, 2013 update

December, 2013

Rain can’t stop us!  We’ll frame in the rain.

We’re still moving along despite all the rain.  All foundation walls and waterproofing are complete on buildings 200, 500 & 600.  The modular block wing wall extensions at Buildings 300 and are approximately 50% complete. Concrete slabs are approximately 90% complete as lower level slabs have been poured at Buildings 200-600 and upper level slabs are in place at Buildings 200, 500 and 600.

Framing is substantially complete at the Community Building and Building 500. Roof trusses have been installed at Building 600 and framing is 90% complete. At Building 200, wall framing is complete at both the terrace and first floors and roof truss installation should begin in the near future. Framing at Building 200 is approximately 60% complete.

Check out some of the latest pictures from the construction site and, as always, please leave comments on this blog or contact us via email (info@peachtreehousing.com) with any comments or concerns you may have.







Wednesday, December 4, 2013

November, 2013 update

November, 2013
Now the fun starts!  Framing underway at the community building!
Construction of building structures has progressed well. Construction of all foundation walls and waterproofing is now complete and modular-block wing wall extensions have been completed at buildings 200, 500, and 600. Both under and over-slab plumbing is under way on all buildings and complete on three.
Concrete slabs have been poured at the Community Building, at the lower side of Building 200, and at the upper and lower sides of buildings 500 and 600.
Framing activities have just commenced. Framing is currently under way at the Community Building which is estimated to be around 75% framed. Framing of the lower-level walls was also found to be under way at Building 600. A limited amount of framing materials is currently on-site including floor trusses for Building 600. Framing progress is expected to increase now that the Thanksgiving holiday is over.

Check out some of the latest pictures from the construction site and, as always, please leave comments on this blog or contact us via email (info@peachtreehousing.com) with any comments or concerns you may have.






Wednesday, October 30, 2013

October, 2013 update

Grading almost complete and footings are being poured.
Mass grading is almost complete.  Installation of site utilities has progressed and installation of the water main, sanitary sewer and storm drainage is now complete along the west side of the gas pipeline right-of-way.  Under-slab plumbing and perimeter strip footings are now complete at Buildings 100, 500 and 600.  Next month we should start framing.

Check out some of the latest pictures from the construction site and, as always, please leave comments on this blog or contact us via email (info@peachtreehousing.com) with any comments or concerns you may have.







Friday, September 27, 2013

Site prepping for slab pouring-September, 2013

The lower slabs on all buildings are at sub-grade.  The sewer main and service is in at four out of five buildings.  Foundation wall footings are in at three out of five buildings.  We’re moving right along and staying on schedule!

Check out some of the latest pictures from the construction site and, as always, please leave comments on this blog or contact us via email (info@peachtreehousing.com) with any comments or concerns you may have.






Thursday, August 29, 2013

Here we go!!-August 2013

We’ve started construction and things are officially moving along.  The initial clearing of the site is complete.  Erosion control devices are in place.  The construction entrance is complete and any driving by the site can see that we’re hard at work! 


Check out some of the latest pictures from the construction site and, as always, please leave comments on this blog or contact us via email (info@peachtreehousing.com) with any comments or concerns you may have.