December, 2013
Rain can’t stop us!
We’ll frame in the rain.
We’re still moving along despite all the rain. All foundation walls and waterproofing are
complete on buildings 200, 500 & 600. The modular block wing wall
extensions at Buildings 300 and are approximately 50% complete. Concrete slabs
are approximately 90% complete as lower level slabs have been poured at
Buildings 200-600 and upper level slabs are in place at Buildings 200, 500 and
600.
Framing is
substantially complete at the Community Building and Building 500. Roof trusses
have been installed at Building 600 and framing is 90% complete. At Building
200, wall framing is complete at both the terrace and first floors and roof
truss installation should begin in the near future. Framing at Building 200 is approximately
60% complete.
Check out some of the latest pictures from the construction