Friday, August 3, 2012
July 2012 Update
Saturday, June 30, 2012
June 2012 Update
Good news! Our community center is now open and we are accepting applications in our new building. In other news on the property, flooring is being installed in the units, sidewalks are now completely in, all of the irrigation lines are in, the planting of shrubs has commenced and all of the site lighting is installed.
We expect to recieve certificates of occupancy for some of our buildings in July and for some of our new residents to begin moving into their new homes!
Check out some of the latest pictures from the construction site and, as always, please leave comments on this blog or contact us via email (conners.village@gmail.com) with any comments or concerns you may have.
We expect to recieve certificates of occupancy for some of our buildings in July and for some of our new residents to begin moving into their new homes!
Check out some of the latest pictures from the construction site and, as always, please leave comments on this blog or contact us via email (conners.village@gmail.com) with any comments or concerns you may have.
Thursday, May 31, 2012
May 2012 Update
It has been a busy month at Conners Senior Village. All exterior paint is now complete. HVAC systems are now installed. Sidewalks are 25% complete. The main entries to our property are now being completed. The landscaper has begun installing the irrigation lines.
We expect our community center will open in early June and our leasing team will be accepting applications in our brand new building!
Check out some of the latest pictures from the construction site and, as always, please leave comments on this blog or contact us via email (conners.village@gmail.com) with any comments or concerns you may have.
Monday, April 30, 2012
April 2012 Update
Exterior finishes are now in the completion stage and interior finishes are in progress on all buildings. Doors, trim, cabinets, fixtures, interior painting and flooring are now being installed in all buildings at one stage or another.
Despite our early weather delays, we are on track to finish early and expect to be ready for occupancy by July 1st!
Check out some of the latest pictures from the construction site and, as always, please leave comments on this blog or contact us via email (conners.village@gmail.com) with any comments or concerns you may have.
Despite our early weather delays, we are on track to finish early and expect to be ready for occupancy by July 1st!
Check out some of the latest pictures from the construction site and, as always, please leave comments on this blog or contact us via email (conners.village@gmail.com) with any comments or concerns you may have.
Saturday, March 31, 2012
March 2012 Update
Good weather is starting to settle in...
All buildings are now dried in. Rough-in of the mechanical, electrical and plumbing systems has been completed in all buildings. Wall insulation is complete in all buildings.
Now we are really getting somewhere!
Check out some of the latest pictures from the construction site and, as always, please leave comments on this blog or contact us via email (conners.village@gmail.com) with any comments or concerns you may have.
All buildings are now dried in. Rough-in of the mechanical, electrical and plumbing systems has been completed in all buildings. Wall insulation is complete in all buildings.
Now we are really getting somewhere!
Check out some of the latest pictures from the construction site and, as always, please leave comments on this blog or contact us via email (conners.village@gmail.com) with any comments or concerns you may have.
Wednesday, February 29, 2012
February 2012 Update
Finally we are nearly dried in on the majority of our buildings and can combat mother nature. Framing activities are substantially complete. Roofing is complete on buildings 2, 4-9. Mechanical, Electrical and Plumbing rough ins are complete on all buildings.
Wall insulation is installed on buildings 5-7 and 9.
More progress!!
Check out some of the latest pictures from the construction site and, as always, please leave comments on this blog or contact us via email (conners.village@gmail.com) with any comments or concerns you may have.
Wall insulation is installed on buildings 5-7 and 9.
More progress!!
Check out some of the latest pictures from the construction site and, as always, please leave comments on this blog or contact us via email (conners.village@gmail.com) with any comments or concerns you may have.
Tuesday, January 31, 2012
January 2012 Update
In spite of the pestering rain, we are making good progress with regards to construction. Installation of all building foundations, under-slab plumbing and concrete slabs are complete. Framing activities are under way on all buildings.
Installation of the roofing is complete on buildings 6 and 9. Rough-in of the mechanical, electrical and plumbing systems is now under way at several buildings.
Progress is being made!
Check out some of the latest pictures from the construction site and, as always, please leave comments on this blog or contact us via email (conners.village@gmail.com) with any comments or concerns you may have.
Installation of the roofing is complete on buildings 6 and 9. Rough-in of the mechanical, electrical and plumbing systems is now under way at several buildings.
Progress is being made!
Check out some of the latest pictures from the construction site and, as always, please leave comments on this blog or contact us via email (conners.village@gmail.com) with any comments or concerns you may have.