Wednesday, June 18, 2014

May, 2014 update

Installation of curb and gutter is approximately 85-90% complete and fine grading to be similarly complete. Concrete sidewalk installation was found to be approximately 75% complete.

Construction of building structures has progressed to substantial completion. Installation of foundation walls, footings, under-slab plumbing, concrete slabs, and rough framing has been completed. Dry-in activities are complete as all roofing, house wrap, window and entry door/patio door installation are now complete.
Exterior finishes continue to progress. Installation of brick veneer is now complete at each residential building and is approximately 80% complete at the community building.

Interior finishes have progressed fairly well and are limited to Buildings 200, 500 and 600. Installation and finishing of drywall, the prime coat of paint, interior trim and door installation, LVT flooring in the kitchens, and sheet vinyl flooring in the bathrooms is complete at each of these buildings. Cabinet installation is currently complete at Building 500 and 600 and underway at Building 200. Electrical device installation is underway at Building 500 and 600.


Check out some of the latest pictures from the construction site and, as always, please leave comments on this blog or contact us via email (info@peachtreehousing.com) with any comments or concerns you may have.