Wednesday, February 19, 2014

January, 2014 update

January, 2014

Moving along…

Framing activities continue to progress and are 65-70% complete. Framing is complete at the Community Building, Building 200 and Building 500. Installation of roof decking was underway at Building 600. Stair and deck framing is complete at Buildings 200 and 500.

Dry-in activities have also progressed as roofing is now in place at the Community Building, Building 200, and Building 500. MEP rough-in is now underway. Plumbing rough-in was is 90% complete at Buildings 200 and 500, with only installation of tubs remaining to be completed. Fire sprinkler and electrical rough-in are complete at Buildings 200 and 500. HVAC rough-in is complete at Building 500 and approximately 90% complete at Building 200 and the Community Building.

Check out some of the latest pictures from the construction site and, as always, please leave comments on this blog or contact us via email (info@peachtreehousing.com) with any comments or concerns you may have.