Friday, January 3, 2014

December, 2013 update

December, 2013

Rain can’t stop us!  We’ll frame in the rain.

We’re still moving along despite all the rain.  All foundation walls and waterproofing are complete on buildings 200, 500 & 600.  The modular block wing wall extensions at Buildings 300 and are approximately 50% complete. Concrete slabs are approximately 90% complete as lower level slabs have been poured at Buildings 200-600 and upper level slabs are in place at Buildings 200, 500 and 600.

Framing is substantially complete at the Community Building and Building 500. Roof trusses have been installed at Building 600 and framing is 90% complete. At Building 200, wall framing is complete at both the terrace and first floors and roof truss installation should begin in the near future. Framing at Building 200 is approximately 60% complete.

Check out some of the latest pictures from the construction site and, as always, please leave comments on this blog or contact us via email (info@peachtreehousing.com) with any comments or concerns you may have.