Wednesday, October 30, 2013

October, 2013 update

Grading almost complete and footings are being poured.
Mass grading is almost complete.  Installation of site utilities has progressed and installation of the water main, sanitary sewer and storm drainage is now complete along the west side of the gas pipeline right-of-way.  Under-slab plumbing and perimeter strip footings are now complete at Buildings 100, 500 and 600.  Next month we should start framing.

Check out some of the latest pictures from the construction site and, as always, please leave comments on this blog or contact us via email (info@peachtreehousing.com) with any comments or concerns you may have.